What safety stock is
Safety stock is the extra stock you keep so you don't run out when sales jump or a delivery arrives late. It sits under your normal stock and only gets used when something goes wrong.
Too little and a bestseller sells out while you wait for the supplier. Too much and cash sits on a shelf. This calculator gives you a number for each product, so the buffer is a decision rather than a guess.
How the calculator works
The calculator offers two methods.
- Max and average is the simple one. Enter your highest normal daily sales, your average daily sales, your longest recent lead time and your average lead time. It covers the case where a busy spell and a slow delivery happen together.
- Standard deviation needs a little more data. Enter your average daily sales, the standard deviation of your daily sales, your average lead time and a service level. The service level is how often you want to avoid running out during a reorder cycle, such as 95% of the time.
Both methods show sales during lead time, a reorder point that includes the buffer and, if you add a unit cost, the cash held in safety stock. Part units are rounded up.
The safety stock formulas
| Figure | Formula |
|---|---|
| Safety stock (max and average) | (Max daily sales × max lead time) − (average daily sales × average lead time) |
| Safety stock (standard deviation) | Z × standard deviation of daily sales × √ average lead time |
| Sales during lead time | Average daily sales × average lead time |
| Reorder point | Sales during lead time + safety stock |
| Cash in safety stock | Safety stock × unit cost |
Z comes from the service level: 1.28 for 90%, 1.65 for 95%, 1.96 for 97.5% and 2.33 for 99%. A higher service level means a bigger buffer.
Worked example
A candle brand sells 6 of its bestselling scent a day on average, and 9 on a busy day. Its supplier usually takes 21 days, but the slowest recent order took 28. Each candle costs $4 to make.
- Max and average method: (9 × 28) − (6 × 21) = 252 − 126 = 126 units
- Sales during lead time: 6 × 21 = 126 units
- Reorder point: 126 + 126 = 252 units
- Cash in safety stock: 126 × $4 = $504
The brand also has a few months of daily sales, with a standard deviation of 2 units. At a 95% service level the standard deviation method gives 1.65 × 2 × √21 = 15.12, rounded up to 16 units. The reorder point is then 126 + 16 = 142 units, and the buffer holds $64 of stock.
The two answers differ a lot. The max and average method plans for your worst day and your slowest delivery at the same time, so it usually gives a bigger buffer. The standard deviation method assumes daily sales vary around the average in a fairly even way and that lead time stays close to the average.
Tips and common mistakes
- Pick realistic maximums. Use your busiest normal day, not a one-off spike from a viral post. A rare peak can double your buffer.
- Measure lead time from your records. Use how long recent orders actually took, from placing the order to stock ready to sell.
- Use the same time unit throughout. If you work in weeks, enter weekly sales and lead time in weeks.
- Don't apply one buffer to every product. Keep more for bestsellers with long or unreliable lead times and less for slow lines.
- Count all channels. A single wholesale order can use up a week of retail sales.
- Review each season. Sales and supplier lead times change, so the buffer should too.
Put your safety stock to work
Safety stock only helps if you reorder on time. Plug your buffer into the reorder point calculator to see when your next order is due. To see how long your stock sits overall, use the inventory turnover calculator, and to check how fast stockists sell your products, try the sell-through rate calculator. When your stockists reorder from you, an order form keeps their orders clear and complete.